Maintain reliable transmission network services at Sydenham Terminal Station Regulatory Investment Test – Transmission

18/08/2021
Market Network Service Provider
StageDraft Report
ConvenorAEMO NSP
Initiated18/08/2021
Accepting submissions?No
Submissions close04/10/2021

Project Assessment Draft Report – Summary

AusNet Services is undertaking this Regulatory Investment Test for Transmission (RIT-T) to evaluate options to maintain reliable transmission network services at Sydenham Terminal Station (SYTS).

The Project Specification Consultation Report (PSCR), which represents the first step in the RIT-T process in accordance with clause 5.16 of the National Electricity Rules (NER) and section 4.2 of the RIT-T Application Guidelines was published in December 2020. This report, the Project Assessment Draft Report (PADR), is the second stage of the RIT-T and provides information about the draft conclusions of the RIT-T.

No non-network proposals were received during the RIT-T PSCR consultation.

The preferred option to address the asset failure risk at SYTS is an integrated replacement with gas insulted switchgear (GIS).

AusNet Services welcomes written submissions on the issues and the credible options presented in this PADR. Submissions should be emailed to rittconsultations@ausnetservices.com.au on or before 4 October 2021. In the subject field, please reference ‘RIT-T PADR Sydenham Terminal Station.’

X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm