This consultation on the Metrology Procedure: Part A and Part B was undertaken in response to a request from the NSW Roads and Maritime Services advised AEMO of its intention to operate its traffic signal installations that are fitted with LED lamps in a dimmed mode to reduce energy consumption.
The consultation was conducted under clause 7.1.4 of the National Electricity Rules (Rules) in accordance with the Rules consultation procedures in clause 8.9 of the Rules.
A consequence of the NSW Roads and Maritime Services request was to amend the Metrology Procedure to incorporate the methodology to facilitate the calculation of metering data for traffic signal operating in dimmed mode.
The consultation has now been completed, and AEMO has published the Final Determination and Report.
Effective date of the amended Metrology Procedure is 15 May 2015.
Metrology Procedure Traffic Signal Dimming Final Determination Report 20 January 2015 | 500 KB (.pdf) |
Metrology Procedure Part A v5.30 Final Determination Traffic Signal Dimming Change Marked 20 January 2015 | 964 KB (.pdf) |
Metrology Procedure Part A v5.30 Final Determination Traffic Signal Dimming Clean 20 January 2015 | 898 KB (.pdf) |
Metrology Procedure Part B v5.30 Final Determination Traffic Signal Dimming Change Marked 20 January 2015 | 1 MB (.pdf) |
Metrology Procedure Part B v5.30 Final Determination Traffic Signal Dimming Clean 20 January 2015 | 1 MB (.pdf) |
Second Stage of Rules Consultation
Metrology Procedure Traffic Signal Dimming Draft Determination Report 20 November 2014 | filesize: 500 KB (.pdf) |
Metrology Procedure Part A and Part B v5.30 Stage 2 Participant Response Pack 20 November 2014 | filesize: 47.5 KB (.docx) |
Metrology Procedure Part A v5.30 Draft Determination Traffic Signal Dimming Change Marked 20 November 2014 | filesize: 970 KB (.pdf) |
Metrology Procedure Part B v5.30 Draft Determination Traffic Signal Dimming Change Marked 20 November 2014 | filesize: 1.00 MB (.pdf) |
Second Stage Consultation Participant Responses
Metrology Procedure Part A and Part B AGL Response Pack 20 November 2014 | 500 KB (.pdf) |
Metrology Procedure Part A and Part B EA 20 November 2014 | 47.5 KB (.docx) |
First Stage Rule Consultation
Metrology Procedure Part A and Part B v5.30 Change Pack - Initial Consultation 18 September 2014 | filesize: 362 KB (.pdf) |
Metrology Procedure Part A and Part B v5.30 Participant Response Pack 18 September 2014 | filesize: 47.8 KB (.doc) |
Metrology Procedure Part A v5.30 Draft Traffic Signal Dimming Change Marked 18 September 2014 | filesize: 1.02 MB (.pdf) |
Metrology Procedure Part B v5.30 Draft Traffic Signal Dimming Change Marked 18 September 2014 | filesize: 999 KB (.pdf) |
First Stage Consultation Participant Responses
Ausgrid Submission - AEMO Metrology Procedure Part A and B First Stage Consultation - 24 Oct 2014 20 November 2014 | filesize: 67.1 KB (.pdf) |
Ausgrid - Metrology Procedure Part A & Part B v5.30 Participant Response Pack Initial - 24 Oct 2014 20 November 2014 | filesize: 76.3 KB (.pdf) |
Endeavour Energy - Metrology Procedure Part A & Part B v5.30 Participant Response Pack v1.0 20 November 2014 | filesize: 274 KB (.pdf) |
Energy Australia - Metrology Procedure Part A and Part B v5.30 Response 20 November 2014 | filesize: 274 KB (.pdf) |
Origin - Metrology Procedure Part A & Part B v5.30 Participant Response Pack 20 November 2014 | filesize: 269 KB (.pdf) |