Powerlink has recently published a ‘Project Assessment Conclusions Report’ (PACR) to address the reliability of supply to Nebo local area.
Nebo Substation was established in the late 1970s to be a major injection point and major 275kV switchyard in the state-wide transmission network, connecting North and South Queensland whilst providing bulk supplies to several key areas, including Mackay and Pioneer Valley. Two 132/11kV transformers and associated primary plant connect the Powerlink substation to the Ergon Energy (part of the Energy Queensland Group) network at Nebo supplying the local area.
The 132/11kV power transformers (Transformer 3 and Transformer 4) and associated 11kV primary plant are nearing the end of their technical lives, with an increasing risk of failure. The failure of a transformer or associated primary plant can result in an extensive replacement timeframe increasing the risk of loss of supply to the local area, and in extreme cases, could present a risk to the safety of personnel.
Planning studies have confirmed there is a long-term requirement to continue to supply the existing electricity services provided by Nebo Substation. Powerlink must therefore take action to avoid the increasing likelihood of unserved energy and the emerging risks arising from failure of the ageing transformers and primary plant at Nebo, and ensure customers are provided with a reliable and safe supply of electricity.
In September 2023 Powerlink published a ‘Project Specification Consultation Report’ (PSCR) identifying the proposed preferred option to address the risks and claiming exemption from producing a ‘Project Assessment Draft Report’ as allowed for under NER Clause 5.16.4(z1).
There were no submissions received in response to the PSCR, which closed in December 2023. As a result, no additional credible options that could deliver a material market benefit have been identified and the outcomes of the economic analysis contained in the PACR remain unchanged from those published in the PSCR.
The PACR recommends implementation of Option 1, the replacement of both transformers and associated primary plant by 2025. The indicative capital cost of the RIT T project for the preferred option is $11.5 million in 2022/23 prices. Powerlink is the proponent of this network project.
In accordance with the requirements of the Rules, a summary of the PACR has been made available on AEMO’s website. A copy of the PACR can be obtained from the Powerlink Website on the RIT-T Consultations page or by emailing networkassessments@powerlink.com.au.
-
AEMO manages the day-to-day operations of a number of electricity and gas markets and information services, as well as providing strategic forecasting and planning advice.
-
AEMO has strategic partnerships with institutions and energy brands across Australia and globally, including the Bureau of Meteorology (BOM) and CSIRO.
-
In addition to regular consultations, AEMO runs regular working groups and forums that allow energy stakeholders to discuss issues and share information.
-
The Library captures procedures, guides and major reports that live elsewhere on the site.
-
Australia’s energy system has a governance structure that includes AEMO, the Australian Energy Regulator (AER), the Australian Energy Market Commission (AEMC), the Energy Security Board (ESB) and the Council of Australian Governments (COAG) Energy Council.
-
AEMO is an independent organisation that operates on a user-pays cost-recovery basis, with all operating costs recovered through fees paid by industry participants. Our ownership is shared between government and industry.