Powerlink Queensland - Summary of PADR - Maintaining reliability of supply between Clare South and Townsville South

07/08/2019
Market National Electricity Market
StageProject Assessment Draft Report
ConvenorAEMO NSP
Initiated07/08/2019
Accepting submissions?No
Submissions close23/09/2019

Powerlink has recently published a ‘Project Assessment Draft Report’ (PADR) to address maintaining reliability of supply between Clare South and Townsville South.

The 132kV network between Collinsville and Townsville was developed in the 1960s and 1970s to supply mining, commercial and residential loads. A parallel 275kV network was developed more than a decade later to reinforce supply into Townsville and far north Queensland. Due to their deteriorating condition the 132kV Clare South to Townsville South Transmission lines are now reaching the end of their technical service life. To maintain compliance with the reliability and service standards set out in the National Electricity Rules, Powerlink’s Transmission Authority and applicable regulatory instruments, Powerlink must address the emerging condition risks on these lines.

The first step of the Regulatory Investment Test for Transmission (RIT-T) with respect to maintaining reliability of supply between Clare South and Townsville South was the publication of the Project Specification Consultation Report (PSCR) in November 2018, which invited submissions particularly on the credible options that could address the identified need.

Two submissions proposing non-network solutions were received in response to the publication of the PSCR. Following discussions with the proponents, and detailed analysis of their proposals, it was concluded that the solutions offered were not technically feasible due to their inability to meet the network’s fault level and voltage control requirements for the area. As a result, they could not be considered as credible options to meet the identified need under this RIT-T.

The PADR recommends a 10 year life extension of the coastal line with network reconfiguration by December 2021 and decommissioning of the inland line by December 2022. The indicative capital cost of the RIT-T project for the preferred option is $28.34 million in 2018/19 prices. Powerlink is the proponent of this network project.

In accordance with the requirements of the Rules, a summary of the PADR has been made available on AEMO’s website. A copy of the entire document can be obtained from the Powerlink website on the RIT-T Consultations page or by emailing NetworkAssessments@powerlink.com.au.

Powerlink welcomes submissions on the PADR by the closing date of  Monday 23 September 2019.

Any enquiries in the first instance should be directed to:

Roger Smith
Manager Network and Alternate Solutions
Powerlink Queensland
PO Box 1193
VIRGINIA, QLD 4014
Tel: (+617) 3860 232

X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm