Transgrid PSCR: Maintaining compliance with performance standards applicable to Regentville substation secondary systems

06/05/2024
Market Network Service Provider
StageProject Specification Consultation Report
ConvenorAEMO NSP
Initiated06/05/2024
Accepting submissions?No
Submissions close02/08/2024

Transgrid has published the Project Specification Consultation Report (PSCR) for Maintaining compliance with performance standards applicable to Regentville substation secondary systems. Publication of this PSCR represents the first step in the RIT-T process.

The Regentville substation is a customer connection point supplying Endeavour Energy’s 132 kV network in an area which contains the Nepean Hospital and Richmond RAAF Air Base. The site will remain a connection point to Endeavour Energy into the foreseeable future as outlined in the load forecasts of the 2021 Annual Planning Report.

Secondary systems assets at Regentville substation are facing technological obsolescence, increasing the time to rectify defects and increasing the risk that primary assets at the substation may not be able to reliably operate. This is significant as secondary systems are used to control, monitor, protect and provide communication to facilitate safe and reliable network operation. They are necessary to ensure the secure operation of the transmission network and prevent damage to primary assets when adverse events occur.

The purpose of this PSCR is to examine and consult on options to address the risk of secondary systems failure as a result of technological obsolescence at Regentville substation. The proposed investment will enable us to continue to meet the standards for secondary systems availability set out in the NER, and to avoid the impacts of taking primary assets out of service. Consequently, it is considered a reliability corrective action under the RIT-T.

Two credible network options have been identified that meet the underlying need from a technical, commercial, and project delivery perspective. Option 1 involves the replacement of individual assets and has a capital cost of $11.08 million ($2022-23). Option 2 focuses on a complete in-situ replacement and has a capital cost of $9.35 million ($2022-23). Option 2 has been identified as the preferred option that maximises net benefits to participants in the National Electricity Market (NEM). 

Transgrid welcomes written submissions on materials contained in this PSCR. Submissions are due on 2 August 2024

In accordance with the requirements of the Rules, a summary of the Project Specification Consultation Report is made available on the AEMO website. A copy of the PSCR can be obtained from Transgrid’s website or by emailing regulatory.consultation@transgrid.com.au.