TasNetworks PACR: Project Marinus

30/06/2021
Market Network Service Provider
StageProject Assessment Conclusions Report
ConvenorAEMO NSP
Initiated30/06/2021
Accepting submissions?No

TasNetworks has issued Project Assessment Conclusions Report (PACR) for Project Marinus into the benefits of increased interconnector capacity between Tasmania and Victoria. Project Marinus refers to the 1500 MW high voltage direct current (HVDC) and converter interconnector assets, known as Marinus Link, and the alternating current (AC) transmission investment in Tasmania, known as the North West Transmission Developments. The PACR has been issued in accordance with the requirements of the National Electricity Rules.

A summary of the PACR has been placed on AEMO’s website.

For more information, visit Project Marinus website or contact the Project Marinus team at team@marinuslink.com.au.