Work package 3: Retail

Overview

Several metering and retail procedures need to be updated to reflect the changes required by the WDR Mechanism rule, mainly around the introduction of the new “demand response service provider” (DRSP) role.

Key dates

Publish issues paper  12 October 2020
 Submissions due  17 November 2020
 Publish draft procedure and draft determination  15 December 2020
 Submissions due  2 February 2021
 Publish final procedure and final determination  16 March 2021