Victorian transmission connections process overview

In Victoria, the transmission network is referred to as Declared Shared Network (DSN). It is operated by Declared Transmission System Operators (DTSOs) who are also registered as Transmission Network Service Providers (TNSPs). You may want to check the Victorian Glossary page before reviewing the contents of these pages.

When processing applications to connect to the DSN, AEMO performs some of the responsibilities carried out in other states by the connecting TNSP. AEMO manages the connection process and is the main point of contact for the Connection Applicant. At each stage of the connections process, Connection Applicants should be aware of the roles and responsibilities of different stakeholders, as well as the regulatory arrangements governing the connection process.

The following pages provide information on the process for establishing a new connection or modifying an existing connection to the DSN in Victoria. For information on applications to connect to Victorian distribution networks and any transmission/distribution networks outside of Victoria, see AEMO’s pages on NEM network connections or the website of the relevant connecting Network Service Provider (NSP).

Information on how transmission developments are managed, who gets involved, and how communities can stay informed and contribute to this process in Victoria can be found in AEMO’s Energy Infrastructure in Your Community brochure (see Connection initiatives page).

1. Pre-feasibility

Explore the feasibility of your project and begin discussions with AEMO, landowners and relevant government authorities.

AEMO’s role: provide transmission network data and other information if requested.

2. Enquiry

Submit a connection enquiry to AEMO to determine the information required to submit an application to connect.

AEMO’s role: receive enquiry and coordinate response and provide transmission network data if requested.

3a. Pre-application

Submit Pre-application form to AEMO to initiate key activities being requested as a part of Pre-application. 

AEMO’s role: receive and coordinate assessment of Pre-application.

3. Application

Submit application to connect to AEMO to initiate key activities for a new/modified transmission connection.
AEMO’s role: receive and coordinate assessment of application to connect.

4. Contracts

Having received a complete application to connect, AEMO prepares an offer to connect.

5. Construction

The construction stage begins after all contracts have been executed. The Connection Applicant completes and implements designs, prepares commissioning programs, and finalises supporting information.

AEMO’s role: review construction progress reports, facilitate resolution of any technical issues, and receive and review updated data and other information from the Connection Applicant.

6. Completion

Finalise registration application requirements and provide commissioning plans and test results.

AEMO’s role: review and approve commissioning plans, coordinate testing with operations, as well as review of performance at successive hold points.

 

  For more information, you can email:

  Victorian transmission connection Email us

 

 