Reserve Capacity Tests
AEMO must test Facilities assigned Capacity Credits to ensure they can meet their Reserve Capacity Obligations.
Scheduled Facilities
Scheduled Facilities (or each Separately Certified Component (SCC) of a Scheduled Facility) must be tested twice a year:
- One summer period Reserve Capacity Test (1 October to 31 March)
- One winter period Reserve Capacity Test (1 April to 30 September)
AEMO must endeavour to conduct Reserve Capacity Tests without warning.
Testing must be undertaken for each fuel type the Facility is certified to operate on.
All results are temperature-adjusted to 41 °C and Market Participants must submit a Temperature Dependence Curve at least 10 Business Days before the start of the relevant Reserve Capacity testing period.
For each of the two testing periods, the Facility may optionally pass by observation, up until the deadline. If the Facility passes by observation, it is exempt from being subject to a Reserve Capacity test during the same period. To pass by observation, Facilities (including, where relevant, their SCCs) must operate at a level equivalent to their Required Level, for:
- Non-intermittent Generating Systems (NIGS): two consecutive half-hour Trading Intervals.
- Electric Storage Resources (ESRs): the average performance over the Electric Storage Resource Obligation Duration.
Demand Side Programmes (DSP)
DSPs must undergo two forms of testing:
- One Verification Test between 1 October and 30 November of each year (or, in the case of a new DSP, within 20 Business Days of registration). DSPs must reduce their consumption by at least 10% of the Capacity Credits assigned for one half-hour Trading Interval. Market Participants must notify AEMO at least two Business Days before the test is to be conducted.
- One summer period Reserve Capacity Test: the DSP must reduce its consumption to its Required Level, adjusted to the level of Capacity Credits currently held, for two consecutive half-hour Trading Intervals.
Failed Tests
If a Facility fails a first Reserve Capacity Test, AEMO must re-test the Facility between 14 and 28 days after the first test.
If the Facility fails a second Reserve Capacity Test, its Capacity Credits will be reduced to the maximum output achieved during either test.
The Market Participant may request a third Reserve Capacity Test where a Facility has failed both previous tests. Upon passing the third test, the Capacity Credits will be reinstated, or set at the level of output achieved during the third test.
If a DSP fails a Verification Test, AEMO must reduce its Capacity Credits to 0 MW. The Market Participant may request a second Verification Test to have the Capacity Credits reinstated.
Reserve Capacity Testing Quarterly Reports
-
2024 Reserve Capacity test reports
-
2023 Reserve Capacity test reports
-
15/01/2024
Reserve Capacity test report: 1 October 2023 to 31 December 2023
56.33 KB -
05/10/2023
Reserve Capacity test report: 1 July 2023 to 30 September 2023
58.83 KB -
13/07/2023
Reserve Capacity test report: 1 April 2023 to 30 June 2023
59.48 KB -
14/04/2023
Reserve Capacity test report: 1 January 2023 - 31 March 2023
37.4 KB
-
-
2022 Reserve Capacity test reports
-
06/01/2023
Reserve Capacity test report: 1 October 2022 - 31 December 2022
33.51 KB -
13/10/2022
Reserve Capacity test report: 1 July 2022 - 30 September 2022
54.28 KB -
14/07/2022
Reserve Capacity test report: 1 April 2022 – 30 June 2022
33.41 KB -
13/04/2022
Reserve Capacity test report: 1 January 2022 to 31 March 2022
522.98 KB
-
-
2021 Reserve Capacity test reports
-
12/01/2022
Reserve Capacity test report: 1 October 2021 - 31 December 2021
42.37 KB -
04/10/2021
Reserve Capacity test report: 1 July 2021 – 30 September 2021
39.92 KB -
14/07/2021
Reserve Capacity test report: 1 April 2021 – 30 June 2021
108.25 KB -
15/04/2021
Reserve Capacity test report: 1 January 2021 to 31 March 2021
82.4 KB
-
-
2020 Reserve Capacity test reports
-
07/01/2021
Reserve Capacity test report: 1 October 2020 - 31 December 2020
96.01 KB -
24/09/2020
Reserve Capacity test report: 1 July 2020 - 30 September 2020
89.53 KB -
30/06/2020
Reserve Capacity test report: 1 April 2020 - 30 June 2020
66.84 KB -
31/03/2020
Reserve Capacity test report: 1 January 2020 to 31 March 2020
81.43 KB
-
-
2019 Reserve Capacity test reports
- 1 January 2019 to 31 March 2019 (48 KB, pdf)
- 1 April 2019 to 30 June 2019 (41 KB, pdf)
- 1 July 2019 to 30 September 2019 (45 KB, pdf)
- 1 October 2019 to 31 December 2019 (35 KB, pdf)
-
2018 Reserve Capacity test reports
- 1 January to 31 March 2018 (166 KB, pdf)
- 1 April to 30 June 2018 (148 KB, pdf)
- 1 July to 30 September 2018 (184 KB, pdf)
- 1 October to 31 December 2018 (41 KB, pdf)
-
2017 Reserve Capacity test reports
- 1 October to 31 December 2017 (165 KB, pdf)
- 1 July to 30 September 2017 (170 KB, pdf)
- 1 April to 30 June 2017 (167 KB, pdf)
- 1 January to 31 March 2017 (174 KB, pdf)
-
2016 Reserve Capacity test reports
1 October to 31 December 2016 (167 KB, pdf)
1 July to 30 September 2016 (19 KB, pdf)
1 April to 30 June 2016 (19 KB, pdf)
1 January to 31 March 2016 (174 KB, pdf)
-
2015 Reserve Capacity test reports
1 October to 31 December 2015 (167 KB, pdf)
1 July to 30 September 2015 (19 KB, pdf)
1 April to 30 June 2015 (13 KB, pdf)
1 January to 31 March 2015 (19 KB, pdf)
-
2014 Reserve Capacity test reports
1 January to 31 March 2014 (24 KB, pdf)
1 April to 30 June 2014 (31 KB, pdf)
1 July to 30 September 2014 (15 KB, pdf)
1 October to 31 December 2014 (35 KB, pdf)
-
2013 Reserve Capacity test reports
1 January to 31 March 2013 (18 KB, pdf)
1 April to 30 June 2013 (31 KB, pdf)
1 July to 30 September 2013 (36 KB, pdf)
1 October to 31 December 2013 (31 KB, pdf)
-
2012 Reserve Capacity test reports
1 January to 31 March 2012 (320 KB, pdf)
1 April to 30 June 2012 (65 KB, pdf)
1 July to 30 September 2012 (12 KB, pdf)
1 October to 31 December 2012 (21 KB, pdf)
-
2011 Reserve Capacity test reports
1 January to 31 March 2011 (110 KB, pdf)
1 April to 30 June 2011 (102 KB, pdf)
1 July to 30 September 2011 (113 KB, pdf)
1 October to 31 December 2011 (109 KB, pdf)
-
2010 Reserve Capacity test reports
1 January to 31 March 2010 (113 KB, pdf)
1 April to 30 June 2010 (109 KB, pdf)
1 July to 30 September 2010 (113 KB, pdf)
1 October to 31 December 2010 (109 KB, pdf)
-
2009 Reserve Capacity test reports
1 April to 30 June 2009 (74 KB, pdf)
1 July to 30 September 2009 (113 KB, pdf)
1 October to 31 December 2009 (109 KB, pdf)
-
2006 to 2009 Reserve Capacity test reports
1 October 2008 to 31 March 2009 (330 KB, pdf)
1 October 2007 to 31 March 2008 (38 KB, pdf)
1 July 2007 to 30 September 2007 (50 KB, pdf)
1 April 2007 to 30 July 2007 (53 KB, pdf)
21 September 2006 to 31 March 2007 (50 KB, pdf)
Further information
For further information about Reserve Capacity Testing, please see the WEM Procedure: Reserve Capacity Testing, and clauses 4.25 and 4.25A of the WEM Rules.