PC_2012_04

  • Type: Standard Procedure Change Process
  • Submitter: IMO
  • Title: New Market Procedure for IMS Interface
  • Date Submitted: 03 February 2012
  • Current Status: The new Market Procedure commenced on 1 July 2012.
Event Date Comments
Procedure Change Proposal published 03/02/2012  
Submission period 06/02/2012 - 02/03/2012 The submission period is 20 Business Days from the date the IMO published the notification
Procedure Change Report published 11/06/2012 Can be published any time after the end of the submission period
Amended procedure commences Balancing Market Commencement Day  