Procedure Change- PPCL0016

  • Type: Standard Procedure Change Process
  • Submitter: System Management
  • Title: Commissioning and Testing
  • Date Submitted: 06 December 2010
  • Current Status: Closed. The amended PSOP commenced on 1 August 2011.
Event Date Comments
Procedure Change Proposal published 13/12/2010  
Submission period 14/12/2010 - 13/01/2011 The submission period is 20 Business Days from the date the IMO published the notification
Procedure Change Report published 30/06/2011
Can be published any time after the end of the submission period
The IMO's decision published 14/07/2011 The IMO must publish its decision on the Procedure Change Report within 10 Business Days of publishing the report.
Amended procedure commences 01/08/2011  This date for commencement has been approved by the IMO