Procedure Change- PPCL0007

  • Submitter: System Management
  • Title: Power System Operating Procedure – Operational Data Points for Generating Plant
  • Date First Published on the IMO Website: 13 May 2009
  • Current Status: Closed. The new procedure commenced 1 August 2009

Timeline for this change

Event Date Comments
Procedure Change Proposal Published 13/05/2009  
Submission period 13/05/2009 – 09/06/2009 The submission period is 20 Business Days from the date the IMO published the notification
Procedure Change Report published 17/06/2009 Can be published any time after the end of the submission period.
The IMO’s decision published 01/07/2009 The IMO must publish its decision on the Procedure Change Report within 10 Business Days of publishing the report.
New Procedure Commences 01/08/2009  

Documents related to this Procedure Change Proposal

Submissions received during the Public Submission Period