Procedure Change- PPCL0009

  • Submitter: System Management
  • Title: Power System Operating Procedure – Commissioning and Testing
  • Date First Published on the IMO Website: 15 June 2009
  • Current Status: Closed. The amended procedure commenced 1 September 2009

Timeline for this change

Event Date Comments

Procedure Change Proposal Published

15/06/2009  
Submission period 16/06/2009 – 10/07/2009 The submission period is 20 Business Days from the date the IMO published the notification
Procedure Change Report published 20/07/2009 Can be published any time after the end of the submission period.
Amended Procedure Commences 01/09/2009  