Procedure Change- PPCL0010

  • Submitter: System Management
  • Title: Power System Operation Procedure - Cleansing of Generation Facility MWh Output
  • Date Submitted: 05 June 2009
  • Date First Published on the IMO Website: 25 August 2009
  • Current Status: Commenced 1 November 2009.

Timeline for this change

Event Date Comments
Procedure Change Proposal published 25/08/2009  
Submission Period 26/08/2009 - 22/09/2009 The submissions period is 20 Business Days from the date the IMO published the notification
Procedure Change Report published 30/09/2009 Can be published any time after the end of the submission period
The IMO's decision published 14/10/2009 The IMO must published its decision on the Procedure Change Report within 10 Business Days of publishing the report
Amended Procedure Commences 1/11/2009 This is the tentative commencement date proposed by System Management. This may be subject to change in the IMO's decision.