PC_2012_08
- Type: Standard Procedure Change Process
- Submitter: IMO
- Title: Changes to Market Procedure for Determination of the Maximum Reserve Capacity Price
- Date Submitted: 12 November 2012
- Current Status: The amended Market Procedure commenced on 15 January 2013.
Event | Date | Comments |
---|---|---|
Procedure Change Proposal Published | 12/11/2012 | |
Submission Period | 13/11/2012 - 10/12/2012 | The submission period is 20 Business Days from the date the IMO published the notification |
Procedure Change Report Published | 11/01/2013 | Can be published any time after the end of the submission period |
Amended Procedure Commences | 15/01/2013 |